Client: Russ Berrie Corporation
Value: £24,000
Worldwide distribution company Russ Berrie, formally instructed Birkdale Projects Ltd, to undertake an internal refurbishment in their UK headquarters at Tower Industrial Estate, Eastleigh.
The works included the removal of a number of internal glazed offices and meeting rooms and re-installing these partitions into various locations over both the ground and first floors.
To enable these works to commence and indeed be completed, there were a wide range of ancillary items of re-position which were required within the existing buildings services infrastructure.
These included mains power and IT re-routing from the primary power distribution board and servers, along with the isolation of existing high level lighting, air conditioning and sprinkler systems which were re-positioned and re-commissioned on completion of the core office partitioning.
All low level under floor telecommunications connections and terminals were disconnected and re-connected successfully, without any major disruption to the existing primary IT and communication call centres.